Project Schedule
Updated on July 03, 2018 - Check Regularly for Updates
PROJECT START DATE: T.B.D.
East Side of Dick Smith Street: 7/16/2018
Work Activities:
-
Remove Existing Sidewalk
-
Remove Existing Driveways (Coordinating with Property Owners)
-
Grading/Earthwork for New 8’ Wide Sidewalk
-
Pour New 8’ Wide Concrete Sidewalk
Work Areas:
-
Work will begin on the North end of Dick Smith Street on the East side of the road and proceed South. (Area A)
-
Work will stop at the intersection of Dick Smith Street & Zared Avenue
West Side of Dick Smith Street: 8/16/2018
Work Activities:
-
Remove Existing Sidewalk
-
Remove Existing Driveways (Coordinating with Property Owners)
-
Grading/Earthwork for New 8’ Wide Sidewalk
-
Pour New 8’ Wide Concrete Sidewalk
Work Areas:
-
Work will begin on the North end of Dick Smith Street on the West side of the road and proceed South. (Area B)
-
Work will stop at the intersection of Dick Smith Street & Zared Avenue
​