Project Schedule

Updated on July 03, 2018  - Check Regularly for Updates

PROJECT START DATE: T.B.D.

 

 

East Side of Dick Smith Street: 7/16/2018

                Work Activities:

  • Remove Existing Sidewalk

  • Remove Existing Driveways (Coordinating with Property Owners)

  • Grading/Earthwork for New 8’ Wide Sidewalk

  • Pour New 8’ Wide Concrete Sidewalk

      Work Areas:

  • Work will begin on the North end of Dick Smith Street on the East side of the road and proceed South. (Area A)

  • Work will stop at the intersection of Dick Smith Street & Zared Avenue

 

West Side of Dick Smith Street: 8/16/2018

                Work Activities:

  • Remove Existing Sidewalk

  • Remove Existing Driveways (Coordinating with Property Owners)

  • Grading/Earthwork for New 8’ Wide Sidewalk

  • Pour New 8’ Wide Concrete Sidewalk

               Work Areas:

  • Work will begin on the North end of Dick Smith Street on the West side of the road and proceed South. (Area B)

  • Work will stop at the intersection of Dick Smith Street & Zared Avenue

​